Environment Protection Licence
John Holland Pty Ltd is the holder of the Environment Protection Licence (EPL) for Sydney Metro West – Eastern Tunnelling Package.
Environment, sustainability, community plans and approval documents
The John Holland CPB Contractors Ghella Joint Venture has developed plans, reports and strategies which outline how we will meet the planning approval (SSI 19238057, dated 24 August 2022) for the Sydney Metro West Eastern Tunnelling Package.
Sydney Metro West environmental management documents are available on the Sydney Metro document library
Document Library
EPL Six Month Water Quality Report April to Sept 2024
The bi-annual water monitoring report is prepared in accordance with Condition C23 of the Project Planning Approval. The condition requires reporting of the surface and ground water results as outlined in the Construction Monitoring Programs.
Ancillary Facility – Hunter Street West
The ancillary facility was not identified in the Sydney Metro West Stage 2 EIS. This facility is required for construction material/equipment laydown and craneage. The establishment of the facility requires minimal construction works to establish the site.
Minor Ancillary Facility – Paternoster Row Pyrmont
This minor ancillary facility is located adjacent to the Sydney Metro Pyrmont West construction site, at Paternoster Row, Pyrmont. The facility is required for laydown and site access. The facility will be required until June 2026.
Sydney Metro West – ETP – Construction Environmental Management Plan Rev 6
The Construction Environmental Management Plan (CEMP) explains how environmental outcomes will be met during construction of the Sydney Metro West Eastern Tunnelling Package project. The CEMP is supported by aspect-specific sub plans. The CEMP has been endorsed by the Environmental Representative as required by the Project Approval Condition C10.
Minor Ancillary Facility – Glebe Island Bridge
This minor ancillary facility is located adjacent to the Sydney Metro The Bays construction site, on the Glebe Island Bridge. The facility is required for laydown and storage. The facility will be required until June 2026.
Minor Ancillary Facility – Union Street Pyrmont
This minor ancillary facility is located adjacent to the Sydney Metro Pyrmont East construction site, at Union Street, Pyrmont. The facility is required for change rooms, toilets, first aid room and storage containers. The facility would allow for increased productivity and safety for the Pyrmont East construction site due to the limited space available on site for upcoming construction activities. The facility is approx. 360m2 and includes the footpath, verge and parking lane along the Union Street frontage. The facility will be required until Feb 2025.
Sydney Metro West – ETP – Construction Traffic Management Plan – Pyrmont West_Stage 2 – Excavation Rev 04
The Construction Traffic Management Plan is applicable to the ETP Works at Pymont West. This plan describes site and task specific details and considers the traffic management initiatives that will be established to minimise disruption and ensure the safety of the wide range of stakeholders potentially affected by the works, including but not limited to, motorists, pedestrians, cyclists, public transport users, local residents, business owners and workers engaged in the Project.
Sydney Metro West – ETP – EPL Environmental Monitoring Data Report
As a holder of Environmental Protection Licence (EPL) for a scheduled activity within New South Wales, John Holland is required to upload monthly summaries of monitoring conducted on the Project. This page provides public access to the required environmental monitoring data.
Sydney Metro West – ETP – Construction Traffic Management Plan – Hunter East – Stage 3 -Rev 01
The Construction Traffic Management Plan is applicable to the ETP Works at Hunter St East. This plan describes site and task specific details and considers the traffic management initiatives that will be established to minimise disruption and ensure the safety of the wide range of stakeholders potentially affected by the works, including but not limited to, motorists, pedestrians, cyclists, public transport users, local residents, business owners and workers engaged in the Project.
Sydney Metro West – ETP – Construction Traffic Management Plan – Hunter West – Stage 2 – Rev 01
The Construction Traffic Management Plan is applicable to the ETP Works at Hunter St West. This plan describes site and task specific details and considers the traffic management initiatives that will be established to minimise disruption and ensure the safety of the wide range of stakeholders potentially affected by the works, including but not limited to, motorists, pedestrians, cyclists, public transport users, local residents, business owners and workers engaged in the Project.
Sydney Metro West – ETP – Construction Traffic Management Plan – Hunter West – Stage 1 -Rev 08
The Construction Traffic Management Plan is applicable to the ETP works at Hunter Street for Demo. This plan describes site and task specific details and considers the traffic management initiatives that will be established to minimise disruption and ensure the safety of the wide range of stakeholders potentially affected by the works, including but not limited to, motorists, pedestrians, cyclists, public transport users, local residents, business owners and workers engaged in the Project.
JCG ETP Community Communications Strategy – Revised
The CCS describes JCG’s approach to managing community engagement through communications on the ETP while meeting our contractual and regulatory obligations. It describes the strategy, resources, methodology and communication tools to be used across all ETP worksites and along the ETP tunnel alignment. This Strategy will be updated progressively throughout the ETP and as required.
Sydney Metro West – ETP – EPL Environmental Monitoring Data Report
As a holder of Environmental Protection Licence (EPL) for a scheduled activity within New South Wales, John Holland is required to upload monthly summaries of monitoring conducted on the Project. This page provides public access to the required environmental monitoring data.
Construction Parking and Access Strategy – Stage 1 – Pyrmont & Hunter St – Rev 07
The Construction Parking and Access Strategy (CPAS) is applicable to the construction of the Sydney Metro West – Eastern Tunnelling Package (ETP Works or the Project). This CPAS describes how JCG JV will identify and mitigate impacts resulting from on and off-street parking changes associated with Pyrmont & Hunter St sites during construction of the Project
Sydney Metro West – ETP – Construction Traffic Management Plan – Hunter West – Stage 2 – Rev 01
The Construction Traffic Management Plan is applicable to the ETP Works at Hunter St West. This plan describes site and task specific details and considers the traffic management initiatives that will be established to minimise disruption and ensure the safety of the wide range of stakeholders potentially affected by the works, including but not limited to, motorists, pedestrians, cyclists, public transport users, local residents, business owners and workers engaged in the Project.
Sydney Metro West – ETP – EPL Environmental Monitoring Data Report
As a holder of Environmental Protection Licence (EPL) for a scheduled activity within New South Wales, John Holland is required to upload monthly summaries of monitoring conducted on the Project. This page provides public access to the required environmental monitoring data.
Sydney Metro West – ETP – Construction Traffic Management Plan – Hunter East – Stage 3 -Rev 01
The Construction Traffic Management Plan is applicable to the ETP Works at Hunter St East. This plan describes site and task specific details and considers the traffic management initiatives that will be established to minimise disruption and ensure the safety of the wide range of stakeholders potentially affected by the works, including but not limited to, motorists, pedestrians, cyclists, public transport users, local residents, business owners and workers engaged in the Project.
Sydney Metro West – ETP – Construction Traffic Management Plan – Hunter West – Stage 1 -Rev 07
The Construction Traffic Management Plan is applicable to the ETP Works at Hunter St for Demo. This plan describes site and task specific details and considers the traffic management initiatives that will be established to minimise disruption and ensure the safety of the wide range of stakeholders potentially affected by the works, including but not limited to, motorists, pedestrians, cyclists, public transport users, local residents, business owners and workers engaged in the Project.
Sydney Metro West – ETP – EPL Environmental Monitoring Data Report
As a holder of Environmental Protection Licence (EPL) for a scheduled activity within New South Wales, John Holland is required to upload monthly summaries of monitoring conducted on the Project. This page provides public access to the required environmental monitoring data.
Environmental review – Skinners Hotel Investigation
Investigation works to remove non-significant and intrusive fabric in the form of gyprock that has been installed during internal fit outs for previous commercial occupation of the Skinners Hotel. The investigations are required to determine the protective measures required for the Hotel as demolition progessess at Hunter West
Sydney Metro West – ETP – Hunter St Precinct – Heavy lift Cranage – Rev 01
The Construction Traffic Management Plan is applicable to the ETP Works at Hunter St for crane demob. This plan describes site and task specific details and considers the traffic management initiatives that will be established to minimise disruption and ensure the safety of the wide range of stakeholders potentially affected by the works, including but not limited to, motorists, pedestrians, cyclists, public transport users, local residents, business owners and workers engaged in the Project.
Sydney Metro West – ETP – Pyrmont East – Stage 3 – Tunnelling & Lining Rev 01
The Construction Traffic Management Plan is applicable to the ETP Works at Pyrmont East – Stage 3 – Tunnelling & Lining – Rev 01. This plan describes site and task specific details and considers the traffic management initiatives that will be established to minimise disruption and ensure the safety of the wide range of stakeholders potentially affected by the works, including but not limited to, motorists, pedestrians, cyclists, public transport users, local residents, business owners and workers engaged in the Project.
Sydney Metro West – ETP – Construction Traffic Management Plan (CTMP) – Pyrmont East – Tower crane- Rev 02
The Construction Traffic Management Plan is applicable to the construction of the ETP Works at Pyrmont East during tower crane demobilisation. This plan describes site and task specific details and considers the traffic management initiatives that will be established to minimise disruption and ensure the safety of the wide range of stakeholders potentially affected by the works, including but not limited to, motorists, pedestrians, cyclists, public transport users, local residents, business owners and workers engaged in the Project.
Sydney Metro West – ETP – EPL Environmental Monitoring Data Report
As a holder of Environmental Protection Licence (EPL) for a scheduled activity within New South Wales, John Holland is required to upload monthly summaries of monitoring conducted on the Project. This page provides public access to the required environmental monitoring data.
Visual Amenity Management Sub Plan
The Visual Amenity Management Sub-plan describe how the visual amenity impacts as a result of construction will be managed during construction of the Sydney Metro West Eastern Tunnel Package Project. This is a sub plan of the Construction Environmental Management Plan and has been endorsed by the Environmental Representative.
Consistency Assessment – Pyrmont East Tunnelling
This Consistency Assessment assesses the implementation of alternate noise mitigation measures to minimise noise impacts of tunnelling and associated supporting activities occurring 24 hours per day, seven days a week prior to the completion of the acoustic shed at Pyrmont east.
Sydney Metro West – ETP – Construction Traffic Management Plan (CTMP) -Hunter East – Stage 1 – Tunnel Excavation and Lining – Rev 05
The Site Specific Construction Traffic Management Plan is applicable to the construction of the ETP Works (the Project). The plan describes provide site and task specific details, and considers the traffic management initiatives that will be established to minimise disruption and ensure the safety of the wide range of stakeholders potentially affected by the works, including but not limited to, motorists, pedestrians, cyclists, public transport users, local residents, business owners and workers engaged in the Project. It provides details of how JCG JV will identify, prevent and manage traffic impacts associated with the construction site specific construction scope detailed within the CTMP.
Sydney Metro West – ETP – Construction Traffic Management Plan (CTMP) -Hunter East – Stage 2 – Demolition – Rev 04
The Site Specific Construction Traffic Management Plan is applicable to the Hunter East Demolition. The plan describes provide site and task specific details, and considers the traffic management initiatives that will be established to minimise disruption and ensure the safety of the wide range of stakeholders potentially affected by the works, including but not limited to, motorists, pedestrians, cyclists, public transport users, local residents, business owners and workers engaged in the Project. It provides details of how JCG JV will identify, prevent and manage traffic impacts associated with the construction site specific construction scope detailed within the CTMP.
Sydney Metro West – ETP – Construction Traffic Management Plan (CTMP) – Pyrmont West – Stage 2 – Site Establishment, Excavation & Tunnelling – Rev 02
The Site Specific Construction Traffic Management Plan is applicable to the construction of the ETP Works at Pyrmont West during Site Establishment, Shaft Excavation & Tunnelling. This plan describes site and task specific details and considers the traffic management initiatives that will be established to minimise disruption and ensure the safety of the wide range of stakeholders potentially affected by the works, including but not limited to, motorists, pedestrians, cyclists, public transport users, local residents, business owners and workers engaged in the Project.
Sydney Metro West – ETP – Construction Traffic Management Plan (CTMP) – Pyrmont East – Stage 2 – Site Establishment & Excavation – Rev 06
The Site Specific Construction Traffic Management Plan is applicable to the construction of the ETP Works at Pyrmont East. The plan considers the traffic management initiatives that will be established to minimise disruption and ensure the safety of stakeholders potentially affected by the works, including but not limited to, motorists, pedestrians, cyclists, public transport users, local residents, business owners and workers engaged in the Project. It provides details of how JCG JV will identify, prevent and manage traffic impacts associated with site establishment and excavation at Pyrmont East.
Sydney Metro West – ETP – Construction Traffic Management Plan (CTMP) – The Bays – Stage 2 – Tunnelling Operations – Rev 04
The Site Specific Construction Traffic Management Plan is applicable to the construction of the ETP Works at The Bays during Tunnelling Operations. The plan considers the traffic management initiatives that will be established to minimise disruption and ensure the safety of stakeholders potentially affected by the works, including but not limited to, motorists, pedestrians, cyclists, public transport users, local residents, business owners and workers engaged in the Project. It provides details of how JCG will identify, prevent and manage traffic impacts associated with tunnelling activties at The Bays.
Sydney Metro West – ETP – Construction Parking and Access Strategy (CPAS) – Stage 2 – The Bays – Rev 05
The Construction Parking and Access Strategy (CPAS) is applicable to the construction of the Sydney Metro West – Eastern Tunnelling Package (ETP) Works or the Project. This CPAS describes how JCG will identify and mitigate impacts resulting from on and off-street parking changes associated with The Bays site during construction of the Project.
Sydney Metro West – ETP – Waste Management Sub-plan Rev 2
The Waste Management Sub-plan describe how waste will be managed during construction of the Sydney Metro West Eastern Tunnel Package Project. This is a sub plan of the Construction Environmental Management Plan and has been endorsed by the Environmental Representative.
Sydney Metro West – ETP Pyrmont West Stage 2 Rev 02 CTMP
The Site Specific Construction Traffic Management Plan is applicable to the construction of the ETP Works at Pyrmont West during Site Establishment, Shaft Excavation & Tunnelling. This plan describes site and task specific details and considers the traffic management initiatives that will be established to minimise disruption and ensure the safety of the wide range of stakeholders potentially affected by the works, including but not limited to, motorists, pedestrians, cyclists, public transport users, local residents, business owners and workers engaged in the Project.
Sydney Metro West – ETP – EPL Environmental Monitoring Data Report
As a holder of Environmental Protection Licence (EPL) for a scheduled activity within New South Wales, John Holland is required to upload monthly summaries of monitoring conducted on the Project. This page provides public access to the required environmental monitoring data.
Flora and Fauna Management Sub Plan
The Flora and Fauna Management Sub Plan describes how flora and fauna will be managed during construction of the Sydney Metro West Eastern Tunnelling Package Project. This is a sub plan of the Construction Environmental Management Plan and has been endorsed by the Environmental Representative.
Ancillary Facility – The Bays Truck Marshalling Area
The ancillary facility was not identified in the Sydney Metro West Stage 2 EIS. This facility is required for a new truck marshalling area and for construction material/equipment laydown. The establishment of the facility requires minimal construction works to establish the site.
Minor Ancillary Facility – The Bays Vehicle Parking
The minor ancillary facility is required for construction personnel light vehicle parking. The facility is located at Glebe Island and allows for improved capcacity and safety for vehicle parking.
Detailed Noise and Vibration Impact Statement – Pyrmont Station Addendum OOH tunnelling prior to shed completion
The works assessed in this Addendum include the commencement of the station cavern tunnelling (Stage 2) prior to the full completion of the acoustic shed. The acoustic shed at the Pyrmont East worksite will be partly constructed, including the platforms over the temporary shaft and part of the shed walls. The commencement of excavation of the station cavern will be undertaken outside standard construction hours to allow the shed construction to continue during the standard hours.
Water reuse strategy
The purpose of this Water Reuse Strategy is to describe how JCG JV will consider and apply the sustainable water use practices during the delivery of the Project. In doing so, this Strategy addresses the relevant requirements of the Project Planning Approval, applicable legislation, and contractual requirements, including the Project Deed and Specifications.
Consistency assessment – Skinners Hotel Roof
This Consistency Assessment assesses impacts associated with protective measures required for Skinners Hotel Roof structure. The protective measures required for the Hotel include the removal of a skillion roof extension installed as part of refurbishment works undertaken in 1989, and the reinstatement of the original roof structure
Annual Noise and Vibration Monitoring Report – March 2023 to March 2024
The Annual noise and vibration monitoring report is prepared in accordance with Condition C23 of the Project Planning Approval. The condition requires reporting of the noise and vibration results as outlined in the Construction Monitoring Programs
Biannual Water Monitoring Report – Oct 2023 to March 2024
The bi-annual water monitoring report is prepared in accordance with Condition C23 of the Project Planning Approval. The condition requires reporting of the surface and ground water results as outlined in the Construction Monitoring Programs
Environmental review – Skinners Hotel Temporary Electrical Works
Skinners Hotel basement has been identified by JCG JV as the preferred location for the installation of the Temporary Builders Service (TBS) due to space constraints across the rest of site and AusGrid specifications. The Environmental Review details consistency with the planning approval.
DNVIS Pyrmont Addendum – OOH Tunnelling
“Detailed Noise and Vibration Impact Statement: Pyrmont Addendum – OOH Tunnelling. The works assessed in this Addendum includes low impact roadheader assembly works (Stage 1) and shaft support works (Stage 1A) prior to the full completion of the acoustic shed. The acoustic shed at the Pyrmont East worksite will be partly constructed, including the platforms over the temporary shaft. “
Heavy Vehicle Local Road Report Hunter East and West Construction Sites – (Anzac Bridge) Rev F
The scope of this Heavy Vehicle Local Road (HVLR) report is to provide an additional outboud route required to service the Hunter East and West construction sites towards the west via Anzac Bridge
Detailed Noise and Vibration Impact Statement – Pyrmont Station Addendum OOH deliveries
The works assessed in this Addendum include the unloading of delivery vehicles (including oversized delivery vehicles) delivering the platform and acoustic shed steel to the Pyrmont East worksite, outside standard construction hours.
Heavy Vehicle Local Road Report Pyrmont East and West Construction Sites – Pier St and Darling Drive
The scope of this Heavy Vehicle Local Road (HVLR) report is to provide an additional outboud route that will be used by 19m articulated tracks for haulage of steelwork required for site establishment and the mobilisation / demobilisation of plant and equipment at Pyrmont East and West .
Sydney Metro West – ETP – EPL Environmental Monitoring Report – April 2024
As a holder of Environmental Protection Licences (EPLs) for a scheduled activity within New South Wales, John Holland is required to upload monthly summaries of monitoring conducted on the Project. This report provides public access to the required environmental monitoring data for the period 16 March2024 to 15 April 2024
Air Quality Management Sub Plan
The Air Quality Management Sub-plan describe how air quality (including dust) will be managed during construction of the Sydney Metro West Eastern Tunnel Package Project. This is a sub plan of the Construction Environmental Management Plan and has been endorsed by the Environmental Representative.
Heritage Management Plan
The Heritage Management Plan describes how heritage will be managed during construction of the Sydney Metro West Eastern Tunnel Package Project. This plan forms part of the Construction Environmental Management Plan and has been endorsed by the Environmental Representative and approved by the Department of Planning and Environment.
D39 Consultation Report: Hunter Street Demolition Revised – April 2024
A summary of consultation undertaken in relation to respite periods for high noise impact works associated with demolition at Hunter Street East and West.
Construction Noise and Vibration Management Sub-plan and monitoring program
The Construction Noise and Vibration Management Sub-plan (CNVMP) (Rev 2) and monitoring program describes how noise and vibration will be managed during construction of the Sydney Metro West Eastern Tunnel Package Project. This is a sub plan of the Construction Environmental Management Plan. The CNVMP and monitoring program has been endorsed by the Acoustic Advisor and approved by the Department of Planning and Environment.
Spoil Management Sub Plan
The Spoil Management Sub-plan (Rev 1) describes how excavated material, known as spoil, will be managed during construction of the Sydney Metro West Eastern Tunnel Package Project. This is a sub plan of the Construction Environmental Management Plan and has been endorsed by the Environmental Representative and approved by the Department of Planning and Environment.
Detailed Noise & Vibration Impact Statement – Hunter Street Station
Detailed Noise and Vibration Impact Statement: Hunter Street Station. The DNVIS includes a quantitative assessment of the predicted noise and vibration impacts as a result of construction at Hunter Street The DNVIS includes details on controls and management measures which will be implemented to minimise predicted impacts.
Sydney Metro West – ETP – EPL Environmental Monitoring Report – March 2024
As a holder of Environmental Protection Licences (EPLs) for a scheduled activity within New South Wales, John Holland is required to upload monthly summaries of monitoring conducted on the Project. This report provides public access to the required environmental monitoring data for the period 16 February 2024 to 15 March 2024
Sydney Metro West – ETP – EPL Environmental Monitoring Report – February 2024
As a holder of Environmental Protection Licences (EPLs) for a scheduled activity within New South Wales, John Holland is required to upload monthly summaries of monitoring conducted on the Project. This report provides public access to the required environmental monitoring data for the period 17 January 2024 to 16 February 2024.
Sydney Metro West – ETP – D39 Consultation Report – Pyrmont
A summary of consultation undertaken in relation to respite periods for high noise impact works associated with the Pyrmont construction sites.
Sydney Metro West – ETP – Detail Noise & Vibration Impact Statement – Hunter Street Addendum for demolition haulage
Addendum to the DNVIS for Hunter Street for the OOH load-out and haulage of demolition materials at both Hunter Street sites (East and West) between 5am and 7am, Monday to Saturday. The activity is proposed as Low Noise Impact Work under Condition 23(b) of the approval.
Minor Ancillary Facility – Union Street Pyrmont
This minor ancillary facility is located adjacent to the Sydney Metro Pyrmont East construction site, at Union Street, Pyrmont. The facility is required for change rooms, toilets, first aid room and storage containers. The facility would allow for increased productivity and safety for the Pyrmont East construction site due to the limited space available on site for upcoming construction activities. The facility is approx. 360m2 and includes the footpath, verge and parking lane along the Union Street frontage. The facility will be required until July 2024.
Construction Traffic Management Plan Pyrmont East – Stage 2, Rev 4
The Site Specific Construction Traffic Management Plan is applicable to the construction of the ETP Works at Pyrmont East. The plan considers the traffic management initiatives that will be established to minimise disruption and ensure the safety of stakeholders potentially affected by the works, including but not limited to, motorists, pedestrians, cyclists, public transport users, local residents, business owners and workers engaged in the Project. It provides details of how JCG JV will identify, prevent and manage traffic impacts associated with site establishment and excavation at Pyrmont East.
Construction Parking and Access Strategy (Stage 1) Pyrmont & Hunter Street
The Construction Parking and Access Strategy (Stage 1) (CPAS) is applicable to the construction of the Sydney Metro West – Eastern Tunnelling Package (ETP Works or the Project). This CPAS describes how JCG JV will identify and mitigate impacts resulting from on and off-street parking changes during construction of the Project.
Sydney Metro West – ETP – EPL Environmental Monitoring Report – January 2024
As a holder of Environmental Protection Licences (EPLs) for a scheduled activity within New South Wales, John Holland is required to upload monthly summaries of monitoring conducted on the Project. This report provides public access to the required environmental monitoring data for the period 17 December 2023 to 16 January 2023.
Soil and Water Management Sub Plan Rev 2
The Soil and Water Management Sub-plan and monitoring programs describe how soil, water (surface and groundwater) will be managed during construction of the Sydney Metro West Eastern Tunnel Package Project. This is a sub plan of the Construction Environmental Management Plan and has been endorsed by the Environmental Representative.
Sydney Metro West – ETP – EPL Environmental Monitoring Report – December 2023
As a holder of Environmental Protection Licences (EPLs) for a scheduled activity within New South Wales, John Holland is required to upload monthly summaries of monitoring conducted on the Project. This report provides public access to the required environmental monitoring data for the period 16 November 2023 to 16 December 2023.
Sydney Metro West – ETP – Hunter St Demolition – D39 Consultation Report
A summary of consultation undertaken in relation to respite periods for high noise impact works associated with demolition at Hunter Street East and West.
Sydney Metro West – ETP – EPL Environmental Monitoring Report – November 2023
As a holder of Environmental Protection Licences (EPLs) for a scheduled activity within New South Wales, John Holland is required to upload monthly summaries of monitoring conducted on the Project. This report provides public access to the required environmental monitoring data for the period 16 October 2023 to 16 November 2023.
Detailed Noise and Vibration Impact Statement – Pyrmont Station
Detailed Noise and Vibration Impact Statement: Pyrmont Station The DNVIS includes a quantitative assessment of the predicted noise and vibration impacts as a result of construction at Pyrmont Station. The DNVIS includes details on controls and management measures which will be implemented to minimise predicted impacts.
Biannual Water Monitoring Report – April 2023 to September 2023
The biannual Water Monitoring Report is prepared in accordance with Condition C23 of the Project Planning Approval. The condition requires reporting of the surface and ground water results as outlined in the Construction Monitoring Programs.
Construction Traffic Management Plan – Pyrmont West – Stage 2 – Site Establishment, Shaft Excavation & Tunnelling – Rev 01
The Site Specific Construction Traffic Management Plan is applicable to the construction of the ETP Works at Pyrmont West during Site Establishment, Shaft Excavation & Tunnelling. This plan describes site and task specific details and considers the traffic management initiatives that will be established to minimise disruption and ensure the safety of the wide range of stakeholders potentially affected by the works, including but not limited to, motorists, pedestrians, cyclists, public transport users, local residents, business owners and workers engaged in the Project.
Detailed Noise and Vibration Impact Statement – Tunnelling
Detailed Noise and Vibration Impact Statement: Tunnelling The DNVIS includes an assessment of the predicted noise and vibration impacts as a result of tunnelling from The Bays to CBD. The DNVIS includes details on controls and management measures which will be implemented.
Sydney Metro West – ETP – EPL Environmental Monitoring Report – October 2023
As a holder of Environmental Protection Licences (EPLs) for a scheduled activity within New South Wales, John Holland is required to upload monthly summaries of monitoring conducted on the Project. This report provides public access to the required environmental monitoring data for the period 16 September to 16 October 2023.
Heavy Vehicle Local Road Report for Use of Local Roads Hunter Street East & West Construction Sites
The scope of this Heavy Vehicle Local Road (HVLR) report is in relation to the heavy vehicle routes which are in addition to the approved haulage routes in the EIS. The scope of this HVLR report is to enable travel via the Anzac Bridge to service the Hunter Street East & West sites.
Heavy Vehicle Local Road Report for Use of Local Roads – Hunter St East (Gresham St) Construction Sites
The scope of this Heavy Vehicle Local Road (HVLR) report is in relation to the heavy vehicle routes which are in addition to the approved haulage routes in the EIS. The scope of this HVLR report is to enable travel via Gresham Street in the CBD due to the closure of Loftus Street to vehicular traffic that is going to be implemented by City of Sydney.
Sydney Metro West – ETP – EPL Environmental Monitoring Report – September 2023
As a holder of Environmental Protection Licences (EPLs) for a scheduled activity within New South Wales, John Holland is required to upload monthly summaries of monitoring conducted on the Project. This report provides public access to the required environmental monitoring data for the period 17 August to 15 September 2023.
Heavy Vehicle Local Road Report for Use of Local Roads – Pyrmont East and West Construction Sites
The scope of this Heavy Vehicle Local Road (HVLR) report is in relation to the heavy vehicle routes which are in addition to the approved haulage routes in the EIS. The scope of this Heavy Vehicle Local Road (HVLR) report is to provide an additional outbound route that will be used by 19m articulated trucks for material delivery to the Pyrmont East and West sites.
Sydney Metro West – ETP – EPL Environmental Monitoring Report – August 2023
As a holder of Environmental Protection Licences (EPLs) for a scheduled activity within New South Wales, John Holland is required to upload monthly summaries of monitoring conducted on the Project. This report provides public access to the required environmental monitoring data for the period 17 July to 16 August 2023.
Sydney Metro West – ETP – EPL Environmental Monitoring Report – July 2023
As a holder of Environmental Protection Licences (EPLs) for a scheduled activity within New South Wales, John Holland is required to upload monthly summaries of monitoring conducted on the Project. This report provides public access to the required environmental monitoring data for the period 17 June to 16 July 2023.
Detailed Noise and Vibration Impact Statement – Tunnelling
Detailed Noise and Vibration Impact Statement: Tunnelling The DNVIS includes as assessment of the predicted noise and vibration impacts as a result of tunnelling at Hunter Street. The DNVIS includes details on controls and management measures which will be implemented.
Community Agreement Hunter Street Site Establishment
The purpose of this proposal is to provide the EPA with the required information for the Eastern Tunnelling Package project to seek a community agreement approval under Condition E1 Community Agreements of the Environment Protection Licence (EPL) No.21784. This community agreement would allow for works to be undertaken outside of standard construction hours and weeknights permitted under L5.1 and L5.9, respectively.
Heavy Vehicle Local Road Report for Use of Local Roads – Hunter Street Tower Crane Assembly
The scope of this Heavy Vehicle Local Road (HVLR) report is in relation to the heavy vehicle routes which are in addition to the approved haulage routes in the EIS. There are two additional routes required for the assembly of the Hunter Street East and West tower cranes. The routes are required to provide an inbound route using Gresham Street, and an outbound route using Pitt Street, not currently provided by the approved routes.
Heavy Vehicle Local Road Report for Use of Local Roads – Hunter Street West Construction Site
The scope of this Heavy Vehicle Local Road (HVLR) report is in relation to the heavy vehicle routes which are in addition to the approved haulage routes in the EIS. There are two additional routes required to service the Hunter West construction site. The first route is required to provide an inbound route from the north. The second route is required to service the inbound and outbound access to De Mestre Place, located in the western boundary of the Hunter Street West site. De Mestre Place is currently the only established access to construction site and is therefore essential to the initial establishment phase of the project.
Sydney Metro West – ETP – EPL Environmental Monitoring Report – June 2023
As a holder of Environmental Protection Licences (EPLs) for a scheduled activity within New South Wales, John Holland is required to upload monthly summaries of monitoring conducted on the Project. This report provides public access to the required environmental monitoring data for the period 17 May to 16 June 2023.
Construction Traffic Management Plan Hunter Street West – Stage 1 – Demolition
The Site Specific Construction Traffic Management Plan is applicable to the Hunter Street West Demolition. The plan describes site and task specific details, and considers the traffic management initiatives that will be established to minimise disruption and ensure the safety of the wide range of stakeholders potentially affected by the works, including but not limited to, motorists, pedestrians, cyclists, public transport users, local residents, business owners and workers engaged in the Project. It provides details of how JCG JV will identify, prevent and manage traffic impacts associated with the site specific construction scope detailed within the CTMP.
Eastern Tunnelling Package Water Pollution Impact Assessment
The Water Pollution Impact Assessment (WPIA) outlines the existing conditions in Sydney Harbour and associated waterways and the expected discharge water quality from the Project. The WPIA proposes site specific discharge criteria for the Project Water Treatment Plants.
Sydney Metro West – ETP – Detail Noise & Vibration Impact Statement – The Bays
Detailed Noise and Vibration Impact Statement: The Bays The DNVIS includes as assessment of the predicted noise and vibration impacts as a result of construction works at The Bays site. The DNVIS includes details on controls and management measures which will be implemented.
Construction Traffic Management Plan – Hunter Street Tower Crane Installation
The Site Specific Construction Traffic Management Plan is applicable to the Hunter Street Tower Crane Installation. The plan describes site and task specific details, and considers the traffic management initiatives that will be established to minimise disruption and ensure the safety of the wide range of stakeholders potentially affected by the works, including but not limited to, motorists, pedestrians, cyclists, public transport users, local residents, business owners and workers engaged in the Project. It provides details of how JCG JV will identify, prevent and manage traffic impacts associated with the site specific construction scope detailed within the CTMP.
Construction Traffic Management Plan – Hunter West Demolition
The Site Specific Construction Traffic Management Plan is applicable to the Hunter West Demolition. The plan describes site and task specific details, and considers the traffic management initiatives that will be established to minimise disruption and ensure the safety of the wide range of stakeholders potentially affected by the works, including but not limited to, motorists, pedestrians, cyclists, public transport users, local residents, business owners and workers engaged in the Project. It provides details of how JCG JV will identify, prevent and manage traffic impacts associated with the site specific construction scope detailed within the CTMP.
Construction Traffic Management Plan – Hunter East Demolition
The Site Specific Construction Traffic Management Plan is applicable to the Hunter East Demolition. The plan describes provide site and task specific details, and considers the traffic management initiatives that will be established to minimise disruption and ensure the safety of the wide range of stakeholders potentially affected by the works, including but not limited to, motorists, pedestrians, cyclists, public transport users, local residents, business owners and workers engaged in the Project. It provides details of how JCG JV will identify, prevent and manage traffic impacts associated with the construction site specific construction scope detailed within the CTMP.
Sydney Metro West – ETP – EPL Environmental Monitoring Data Report – May 2023
As a holder of Environmental Protection Licences (EPLs) for a scheduled activity within New South Wales, John Holland is required to upload monthly summaries of monitoring conducted on the Project. This page provides public access to the required environmental monitoring data.
Construction Traffic Management Plan Pyrmont East – Stage 1 – Demolition
The Site Specific Construction Traffic Management Plan is applicable to the construction of the ETP Works at Pyrmont East during Demolition. The plan considers the traffic management initiatives that will be established to minimise disruption and ensure the safety of stakeholders potentially affected by the works, including but not limited to, motorists, pedestrians, cyclists, public transport users, local residents, business owners and workers engaged in the Project. It provides details of how JCG JV will identify, prevent and manage traffic impacts associated with construction at Pyrmont East.
Construction Traffic Management Plan The Bays – Stage 1 – Site Establishment
The Site Specific Construction Traffic Management Plan is applicable to the construction of the ETP Works at The Bays during Site Establishment. The plan considers the traffic management initiatives that will be established to minimise disruption and ensure the safety of stakeholders potentially affected by the works, including but not limited to, motorists, pedestrians, cyclists, public transport users, local residents, business owners and workers engaged in the Project. It provides details of how JCG JV will identify, prevent and manage traffic impacts associated with construction at The Bays.
Sydney Metro West – ETP – EPL Environmental Monitoring Data Report – April 2023
As a holder of Environmental Protection Licences (EPLs) for a scheduled activity within New South Wales, John Holland is required to upload monthly summaries of monitoring conducted on the Project. This page provides public access to the required environmental monitoring data.
Sydney Metro West – ETP – Detail Noise & Vibration Impact Statement – Pyrmont
Detailed Noise and Vibration Impact Statement: Pyrmont The DNVIS includes as assessment of the predicted noise and vibration impacts as a result of demolition and shaft excavation works at Pyrmont. The DNVIS includes details on controls and management measures which will be implemented.
Overarching Construction Traffic Management Plan and Construction Parking and Access Strategy (Stage 1) Pyrmont & Hunter Street
The Overarching Construction Traffic Management Plan is applicable to the construction of the Sydney Metro West – Eastern Tunnelling Package (ETP Works or the Project). This plan describes the overall traffic and transport management strategies, processes and controls common to each area of the project works. It provides details of how JCG JV will identify, prevent and manage traffic impacts associated with the construction of metro stations at The Bays Precinct, Pyrmont and Hunter Street in the Sydney CBD. The Construction Parking and Access Strategy (Stage 1) (CPAS) is applicable to the construction of the Sydney Metro West – Eastern Tunnelling Package (ETP Works or the Project). This CPAS describes how JCG JV will identify and mitigate impacts resulting from on and off-street parking changes during construction of the Project.
Sydney Metro West Eastern Tunnelling Package. Detailed Noise and Vibration Impact Statement: Preliminary Works Hunter Street East
The DNVIS includes as assessment of the predicted noise and vibration impacts of the Preliminary Works at Hunter Street East on sensitive receivers and includes noise & vibration control and management measures.
JCG ETP Small Business Owners Engagement Plan (SBOEP)
The objective of the Small Business Owners Engagement Plan (SBOEP) is to outline how JCG plans to manage the impacts of construction for the operation and continuity of small businesses impacted by delivery of the Eastern Tunnelling Package (ETP).
Construction Traffic Management Plan Pyrmont West – Stage 1 – Demolition
The Site Specific Construction Traffic Management Plan is applicable to the construction of the ETP Works (the Project). The plan describes site and task specific details and considers the traffic management initiatives that will be established to minimise disruption and ensure the safety of the wide range of stakeholders potentially affected by the works, including but not limited to, motorists, pedestrians, cyclists, public transport users, local residents, business owners and workers engaged in the Project. It provides details of how JCG JV will identify, prevent and manage traffic impacts associated with the construction site specific construction scope detailed within the CTMP.
Construction Traffic Management Plan Hunter Street East – Stage 1 – Tunnel Excavation and Lining
The Site Specific Construction Traffic Management Plan is applicable to the construction of the ETP Works (the Project). The plan describes provide site and task specific details, and considers the traffic management initiatives that will be established to minimise disruption and ensure the safety of the wide range of stakeholders potentially affected by the works, including but not limited to, motorists, pedestrians, cyclists, public transport users, local residents, business owners and workers engaged in the Project. It provides details of how JCG JV will identify, prevent and manage traffic impacts associated with the construction site specific construction scope detailed within the CTMP.
Sydney Metro West Eastern Tunnelling Package. Detailed Noise and Vibration Impact Statement: Low Impact Works (Project Wide).
The DNVIS includes as assessment of the predicted noise and vibration impacts of the Low Impact Works (Project Wide) on sensitive receivers and includes noise control and management measures.
Sydney Metro West Eastern Tunnelling Package. Detailed Noise and Vibration Impact Statement: Preliminary Works (Project Wide).
The DNVIS includes as assessment of the predicted noise and vibration impacts of the Preliminary Works (Project Wide) on sensitive receivers and includes noise control and management measures.
Sydney Metro West: The Bays to Sydney CBD, Conditions of Approval.
The Conditions of Approval issued by the Minister for Planning for critical State Significant Infrastructure application no. SSI 19238057.